Kayseri Landfill Gas Regenerative Siloxane Removal System

We have commissioned the Regenerative Siloxane Removal System with a capacity of 20,000 Nm3/h at the Seymen Landfill Gas Power Generation Facility of R Enerji Elektrik Üretim A.Ş.
  • Product
  • Capacity
    2500 Nm³/h
  • Customer
    R Enerji Elektrik Üretim A.Ş.
  • Year
    2022
  • Location
    Kayseri

About The Plant

A Regenerative Siloxane Removal System with a capacity of 2,500 Nm³/h will be installed for the power generation facility from landfill gas with an installed capacity of 7 MW in the sanitary landfill located in Boğazköprü, Kayseri. In the project scope; engineering, manufacturing, assembly, automation, and commissioning works have been carried out.